Kevin explains: “When we got involved with the converged network for the first phase of Battersea Power Station, it was the biggest brick building in Europe and possibly the biggest building site in the country. Imagine the number of contractors and trades involved. Each working to their own deadlines, with limited access to site.
“…there’s a real danger that someone will come and plonk a massive aircon unit in front of the AP…”
“Everything is interconnected, like a giant eco-system. We need power to install the network. Certain fixings need to be finished before we can mount Access Points (AP’s). But if you do it too soon, there’s a real danger that someone will come and plonk a massive aircon unit in front of the AP; or reconfigure an internal wall, compromising Wi-Fi for ever more.”